Yorkshire Water stopped the screw the same night.

SAM4 raised an urgent bottom-bearing alert on a 250 kW inlet screw at Knostrop STW. Yorkshire Water stopped it within hours, found the bearing collapsed, and had the screw back in service in 12 days rather than months.

£150kConfirmed value
Same nightFrom alert to the screw being stopped and checked
12 daysOf downtime, rather than months for a complete failure
AssetArchimedes screw pump
Key result£150k saved
The customer and the asset

A low-level inlet screw at Knostrop STW

Yorkshire Water provides water and wastewater services across Yorkshire. Knostrop STW in Leeds is one of its largest wastewater treatment works.

The asset is a low-level inlet screw: a 250 kW Archimedes screw pump, driven through a belt and gearbox and controlled by a VFD. SAM4 monitors it from the motor control cabinet.

What SAM4 detected

An urgent bottom-bearing failure alert

On Sunday 11 October 2026, SAM4 raised an urgent bottom-bearing failure alert on the screw. It advised Yorkshire Water to stop the screw or switch duty as soon as possible, then inspect.

Two bearing failure indicators had been flat through the morning. From late afternoon they rose sharply and stayed elevated. The alert went out on that pattern.

The response

From alert to inspection in hours

12 October: a Black Alert was raised with Yorkshire Water's duty manager at 00:38. Based on that alert, the site stopped the screw and checked it the same night.

13 October: Samotics and a Yorkshire Water engineer were on site. The bottom bearing was confirmed collapsed.

24 October: the bearing was replaced ahead of plan and the screw went back into service, after 12 days of downtime.

The outcome

12 days of downtime instead of months

SAM4 named the asset, the component and the action, and Yorkshire Water found exactly that: a collapsed bottom bearing. The bearing is submerged and can't be inspected without major downtime.

SAM4 picked this up at the far end of a belt and gearbox drive train, from current and voltage measured at the motor control cabinet rather than at the screw itself.

Acting on the alert kept the outage to 12 days. A complete failure could have meant months: a new screw to manufacture on a long lead time, a new concrete trough, and heavy cranes on site.

"The biggest benefit of the alert was that it enabled us to stop the screw quickly enough to prevent major secondary damage. We avoided a costly full screw replacement and had it back up and running inside a couple of weeks rather than many months."

Michael Horner, Reliability Engineer, Asset Delivery & Engineering, Yorkshire Water